The chip and seal portion of the summer street program in Mt. Carmel has wrapped up with fog sealing scheduled for next month. Public Works director Mike Gidcumb told the city council that fog sealing will be done on July 8th and possibly the 9th.
Also on July 9th, Huff Sealing will be in Mt. Carmel to seal pavement cracks along Market Street between 3rd and 9th Streets. City Engineer Dave Dallas said the work will begin at 5:30am on July 9th at 5th and then head toward 3rd Street. Then, return to 5th Street and work toward 9th.