As Mt. Carmel motorists impatiently wait for the 9th Street repaving to begin, some might have been confused to see some recent work on the crumbling surface…
That’s Mt. Carmel Mayor Joe Judge who said crews this Spring will begin working on sidewalk intersections before the repaving starts…
Judge said he anticipates Howell Paving to start the 9th Street re-asphalting to start in late May or early June. Howell Paving has allocated 111 working days for the project with a completion date no later than October 25th, 2025.