Look for construction activity to ramp up next week at Wabash General Hospital. At Monday’s WGH board of directors meeting, hospital president/CEPO Karissa Turner updated board members on the medical office building construction project….
Turner said the MRI truck will be relocated to the north side of the hospital campus on June 3rd. The main entrance of the hospital will be shut down on June 1st….
Turner said once the medical office building is occupied, the oncology building will be torn down March 25th of next year. Turner said work on the addition to the orthopedic clinic will start June 7th and completed by January 12th of next year with renovations of the orthopedic clinic done by next April. In the main hospital, Turner said the kitchen will close October 21st and remain closed until February 4th. She said plans are already in motion to cover the time the kitchen is closed. Turner stressed the construction dates will likely change as the project progresses.