9th Street Project Becoming Closer To Reality

Howell Paving was the lone bidder for the long-awaited resurfacing of 9th Street in Mt. Carmel. The Mattoon company’s bid came in at $3,847,998 for 1.6 miles of resurfacing, ADA improvements, and traffic signal upgrades on 9th Street from two-tenths of a mile east of Empire Street to Cherry Street in Mt. Carmel. The Illinois Department of Transportation reported on its’ website that Howell’s $3.8 million bid was within a reasonable approximation of the estimate. State Senator Terri Bryant has been in contact with I-DOT’s Effingham office and on yesterday’s WSJD Morning Show, she said work could still start at some point this year….

Your browser doesn't support HTML5 audio

TERRI BRYANT ON 9TH ST 8 14 24

The contract calls for the work to be completed in 110 working days.