WSJD 100.5

View Original

City Projects To Ramp Up Next Week

From City Clerk Ryan Turner:

Oak Street / 5th Street Paving (FAU)

 The paving portion of the FAU project is scheduled to begin on 5th street Starting Monday November 1st.

They will then move to Oak Street starting at the Oak and College Drive intersection working their way south until completed.

 The paving portion of the project depending on weather is scheduled to wrap up November 5th.

 Water Line Project 3rd and Walnut area

This project is scheduled to start the week of November 1st. Kieffer Bros is the contractor for this project.