Plans Announced For Mt. Carmel Summer Street Maintenance Program

Mt. Carmel’s summer street maintenance program is set for later this month, weather permitting. Street Commissioner Tom Meeks reports that the chip and seal work will take place July 29th and 30th with the fog sealing of those affected streets scheduled for the following week. Finance Commissioner Eric Ikemire said the motor fuel tax fund, which funds the oil and chip program, currently had a balance of $692,540.

Below is the tentative list of areas targeted for the 2020 program. List is subject to change.

List is tentative and subject to change.

List is tentative and subject to change.